January 3, 2018
Cube Hydro just announced they will pull High Rock Lake down to 7 Feet below
full pool by Friday January 5th. Since they normally plan their generation
schedule in advance you would expect them to give a little more advance notice
of significant fluctuations to property owners. If your boat is still in
the water take whatever precautions are necessary to protect it from damage.
April 6, 2017
Today Cube Hydro representatives met with State Agency and
Stakeholder groups representatives to begin discussions concerning the revisions
to the existing Shoreline Management Plan. Article 407 of the new project
license identified 9 specific items that should be included in the revised SMP
which must be filed for approval by FERC by September 1, 2018. The
consensus of the participants was that many of the updates could likely be
addressed by updating the terminology used previously with terminology supplied
by FERC as the currently accepted standard. Those verbiage updates as well
as the changes negotiated between stakeholders and Alcoa during the relicensing
process and included in the Relicensing Settlement Agreement appear to address
the bulk of the changes required by FERC and could reasonably be accomplished in
a very timely manner. Cube appeared to agree but stated the remaining
changes would take more effort on their part to complete and noted the
possibility of a few NEW changes that have not been discussed in the past.
These included potential changes to the existing "Lap Tree" policy, potential
additional regulations concerning Water Willow, Ski Jump or Slalom Courses and
Floating Trampolines as well as new "Guidance" documents for pier specifications
FERC has also mandated updates to the project Recreation Plan,
Rare Threatened and Endangered Species Plan and the Historic Properties Plan.
All of these plan updates must be completed and submitted to FERC by September
1, 2017. Cube has proposed the
following time schedule to complete the SMP revision process.
April 22, 2016
|
Update Goals and Objectives
|
May 5, 2016
|
Revise the Project Description
|
June 30, 2016
|
Update Appendices A, B, C, D, and Project Maps
|
August 30, 2016
|
Revise Recreation Resources Plan
|
September 29, 2016
|
Revise Environment and Natural Resources Plan
|
November 15, 2016
|
Produce completed DRAFT of the revised SMP
|
November 16 thru December 25
|
Provide 30 day review period
|
January 12, 2017
|
Submit the revised SMP to FERC for approval
|
While this schedule does not accomplish the implementation of
the negotiated SMP changes included in the RSA within 3 months of license
issuance as specified in section 2.4.2 of the RSA, it does provide an
accelerated implementation schedule compared to the two year timeframe specified
in Article 407 of the new license. Cube agreed to investigate the
possibility of a two stage filing with FERC to allow implementation of
negotiated RSA items prior to the complete RSA revision but appeared doubtful
this approach would be allowed by FERC.
At the conclusion of this meeting there were some additional
discussions concerning the Recreation Plan updates, updates to the Cube Website
specified in Appendix B of the new license and their general intentions
concerning future operations as they relate to water levels at all lakes.
Many of the participants were surprised to learn the NEW
access area specified in the RSA for Rowan County and identified in the
Recreation Plan was specified by Alcoa as a "swimming and beach" facility with
NO launch ramps for boats. As there are no existing "Access Areas" within
the project without boat launch ramps the negotiators for this new facility
intended it to be a full and complete "Access Area" as they exist at all other
locations.
Cube is still working on the required updates to their website
to provide the information specified in Appendix B of the license and was
receptive to some usability recommendations as they go forward. Some of
the required data is already available but is scattered on different pages of
the site making it more difficult to view and understand the related
information. One of the welcome additions is the page that allows you to
renew your pier
permits online instead of having to mail documentation back and forth.
If you need to contact Cube Hydro Carolinas concerning any
permitted activities please
contact Karen Baldwin at (704) 422-5525 or
kbaldwin@cubecarolinas.com
As for project operations, they stated there general intent is
to operate within the new lake level regulations as closely as possible to the
way the project has been voluntarily operated over the last ten years. This
would mean keeping High Rock within a 1 to 3 foot below full Pool (-4 foot
maximum) during the recreation season (April 1st thru November 1st) and the remaining lakes within 1 foot of
full pool (-5 foot Maximum at Badin). Most exceptions to this philosophy
would be driven by low inflow to the project as compared to the discharge
requirements throughout the year and the implementation of the Low Inflow
Protocol if necessary.
March 17, 2017
Cube Hydro responded to our last
email with this
reply From Karen Baldwin
stating they are committed to project license compliance and are already working
hard to meet the many compliance deadlines ahead of them this year. She
then went on to assure us they are concurrently beginning work on the updated
Shoreline Management Plan which is due by September 2018.
We were pleasantly surprised on March 14th when we received an
invitation from Jody Smet to the first SMP review meeting. This is not a
public meeting. This meeting will consist of the agency and stakeholder
group representatives that participated in the SMP Issue Advisory Group during
the relicensing negotiations. The goal is to review the recommendations
that were negotiated and submitted to FERC in the Relicensing Settlement
Agreement to verify those recommendations are still appropriate and supported by
the group.
Jody was a APGI contractor during the relicensing negotiations
and worked as a project manager scheduling most of the meetings and tracking the
progress of each group. Seems she was contacted and hired by Cube Hydro
Carolinas this week to manage the processes addressing the future compliance
issues for Cube Hydro. Her familiarity with the participants involved and
the issues that were addressed during the relicensing process should provide a
beneficial jump; start to the processes going forward. Subsequent
conversations with her indicates that Cube may share our belief that many of the
requirements listed in Article 407 of the project license have already been
addressed in the RSA. They appear to be hopeful the SMP updates can be
completed with a minimum amount of new work and could POSSIBLY be submitted to
FERC for review and approval considerably in advance of the September 2018
deadline.
March 8, 2017
Cube Hydro responded to our initial license questions with this
EMAIL
stating:
Article 409 is FERC’s “Standard Land Use Article”, which FERC includes in
all license orders; it is not intended to be Project specific and is subject to
other specific license conditions.
Article 407 is Yadkin Project specific and requires the
licensee to continue implementing the SMP as modified and approved by the
Commission (FERC) in 2000. The current SMP must remain in effect until
FERC approves a revised SMP, which is also required by the Article.
This means that it may be two more years before the negotiated changes
specific to the Shoreline Management Plan and the Recreation Plan
included in the Relicensing Settlement Agreement MIGHT be approved and added to
the plans that FERC has required
Cube Hydro to update. We sent this
RESPONSE expressing our concerns and
offering to help expedite the process of completing the update to these two
plans in any way we could.
March 3, 2017
Last night the High Rock River Rats held their monthly meeting
and invited Cube Hydro Carolinas representative Karen Baldwin to speak to the
local residents concerning the future management of Project 2197 and address any
questions they had concerning the new project licensee. The most common
questions concerned the recent drop of High Rock Lake to more than 4 feet below
full pond and when the changes in the Relicensing Settlement Agreement would be
implemented.
Ms. Baldwin began her presentation by reading this
letter from Mark Gross,
VP Hydro Operations, which states "In granting the new
FERC
License the FERC did not approve or incorporate the
Relicensing
Settlement Agreement (RSA) filed with FERC on May 7, 2007. As
a result, FERC did not approve the modifications to the Yadkin Project
Shoreline Management Plan (SMP) that were included in the RSA."
This statement caused us great concern as almost every change proposed
by Alcoa and all of the Stakeholders involved in many years of
negotiations was included in the RSA. The letter then went on to
identify ONLY the provisions of the Shoreline Management Plan were not
specifically included in the license articles. Article 407 of the
new license specifies that the licensee must file a revised SMP within
two years of license issuance (September 22, 2016) and keep the
current SMP in effect until they are notified by FERC that the
revised SMP is approved. This means that all of the changes to the
SMP negotiated and agreed upon by Alcoa and the participating
Stakeholders will be delayed up to two more years until Cube Hydro has
submitted the revised SMP and FERC has approved it.
After reviewing the new 40 year license it appears
there may be some conflict between Article 407 and Article 409
concerning Private Recreation Facilities. References to Article
407 indicate that the SMP must be updated in order to change the
previously identified "Land Use Classifications" to the currently
accepted FERC standard designations. It goes on to identify that
the licensee referenced in Appendix D of the RSA and the licensee stated
in the existing SMP must be updated to reflect the correct licensee.
Even though Alcoa requested the name "Cube Hydro Carolinas" be
substituted everywhere in the license application, it appears the new
license was actually issued to Alcoa and then the sale of the project
and the change to the name of the licensee was approved at a later date.
Now that the licensee is Cube Hydro Carolinas it appears the referenced
changes to the existing SMP must be done separately since the SMP is not
an actual license document even though it is referenced repeatedly in
the actual license. None of the changes specified to the SMP in
article 407 reference private recreational facilities or the guidelines
established by the licensee for permitting these facilities which was
probably one of the most important questions for those attending the
meeting.
Article 409 on the other hand specifically identifies
the "Use and Occupancy" guidelines that ARE incorporated in the new
license. Article 409b specifically identifies several types of
"Use and Occupancy" activities which DO NOT require prior commission
approval. All of these identified activities ARE the changes many
adjacent property owners fought for during the relicensing process and
have been waiting patiently for throughout the last decade while the
issuance of the new license was delayed.
If you have questions concerning this apparent
contradiction, suggestions for additional changes to the updated SMP
filing that are NOT included in the current RSA or if you would like to
contact Cube Hydro Carolinas concerning any
permitted activities please
contact Karen Baldwin at (704) 422-5525 or
kbaldwin@cubecarolinas.com
September 22, 2016
In case you missed it, today with very little fanfare FERC
issued a new 40 year license to
operate Project 2197. This new license should incorporate all of the
improvements and changes agreed to in the
Relicensing Settlement Agreement negotiated over a 4 year period by
representatives from SHRL and many other interest groups participating in the
FERC Relicensing process.
This should clear the way for Alcoa to proceed with their
proposal to sell Project 2197 to Cube Hydro Yadkin, LLC.
August 13, 2016
It looks like many of the relicensing participants may not
quite be ready to sit by and allow Alcoa and Cube Yadkin to just sell the
project and transfer the licensee for Project 2197 to a completely NEW company
that has only been in existence for a couple of months without a challenge. You
should read the comments of
The State of
NC, NC Dept. of Environmental
Quality, NC
Wildlife Resources,
City of Salisbury,
American
Rivers and
New Energy Capital Partners as well as the
rebuttal by Cube Yadkin to their challenges . Lets hope FERC at least gives
their questions and concerns for the "interests of the Public" as defined in the
Federal Power Act the proper consideration instead of just blindly rubber
stamping the request in the interest of BIG MONEY investor profits and the
significant fees paid to FERC each year based on the energy produced by the
licensee.
August 1, 2016
The Federal Energy Regulatory Commission issued a
notice soliciting "Comments" and
"Motions to Intervene" regarding the
application of APGI to
transfer the FERC License for Project 2197 to Cube Hydro Yadkin, LLC. (an
affiliate of Cube Hydro Carolinas, LLC. which is an Affiliate of Cube Hydro
Partners, LLC.). All of these recently formed PRIVATE Limited Liability
Corporations (July 16, 2016 for Cybe Hydro Yadkin) are all apparently funded by
I Squared Capital which is again a privately held LLC founded and managed by
financial wizard Sadek Wahba who has obviously
identified small independent hydro power generation facilities as an untapped
source of huge financial gains for wealthy investors. The APGI application
requesting approval for "Transfer of License, substitution of Applicant, and
Request for Expedited Consideration attempts to identify this series of
affiliated LLCs as experienced owners and operators of numerous hydro electric
facilities but the list of facilities owned by the Cube Hydro group reveals 14
very small generation facilities which combined only equals a fraction of the
capacity of project 2197. More importantly, nothing listed has a similar
potential to impact an entire River Basin such as the Yadkin-Pee Dee River Basin
covering 7221 square miles in North Carolina and South Carolina.
The Application does state that Cube Hydro Yadkin would be
substituted as the applicant in the still pending (8 years overdue) FERC License
Application for Project 2197 and that they would be bound by the terms included
in the Relicensing Settlement Agreement that was negotiated with the identified
stakeholder groups during the relicensing process.
Throughout the Relicensing Settlement Negotiations for Project
2197 several of the stakeholder groups questioned the "entitlement" of Alcoa to
continue as the future licensee of the project. In the past Alcoa had touted
their Aluminum Smelting operations as providing a great financial benefit to
communities surrounding the project to demonstrate the need/benefit to the
general public in their past FERC license applications. Most of those
positive benefits disappeared with the closing of the facilities and the
discovery of numerous hazardous waste sites surrounding the plant and the
resulting contamination of ground water supplies. Since Duke Power Co. generally
has abundant generation capacity to service all of the communities surrounding
the project and is regulated by the NC Utilities Commission, about the
only positive benefit to the general public for allowing Alcoa to continue as
the project licensee and operating as an unregulated power generator was the
potential to use that license as leverage to force them into cleaning up their
toxic waste sites surrounding the abandoned facilities. It appears this
pending sale of Project 2197 to a group of private financial investors with
virtually NO PUBLIC ACCOUNTING of sale price, their ongoing operations and
subsequent windfall profits driven by the free use of NC natural resources could
become another one of those "Be careful what you ask for, you just might get it"
lessons in life.
If you wish to submit "Comments" or a "Motion to Intervene" in
this process you have until August 30, 2016 to submit your documents to FERC as
outlined in the notification referenced above.
|